Woods Square
Progress | Status |
---|---|
Foundation Works |
Completed
The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
|
Reinforced Concrete Works |
Completed
The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
|
Brick Walls |
Completed
The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
|
Ceiling |
Completed
The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
|
Internal Plastering & Plumbing |
Completed
The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
|
Installation of Electrcial Plant, Sanitary Equipment & Air-conditioning Plant (if any) |
Completed
The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
|
Carpark, Roads and Drain Serving The Building |
Completed
The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
|
T.O.P. |
Obtained
The Purchaser shall pay 25% of the Purchase Price according to the Payment Schedule.
|
*T.O.P date stated here is indicative only and is given based on estimate and information available. T.O.P date may vary over time depending on individual site conditions and situations. Information accurate as of 1 June 2020.